Every new party adds more interfaces than you think
Interfaces between parties grow as n(n−1)/2. Two parties share one interface, five share ten, ten share 45 and twenty share 190.
Headcount grows in a straight line; coordination effort does not. A project with twenty subcontractors needs an interface register, a responsibility matrix and a common data environment with clear ownership, not only more meetings.
We start every engagement by listing the parties and the information that passes between them. It is the cheapest risk register a project will ever write.