Cumulative progress, planned against earned
Progress by zone, planned and actual (%)
Activities driving delay
| Activity | Float | Delay |
|---|---|---|
| Core walls L7 to L12 | 0d | 8d |
| Curtain wall L3 | 4d | 6d |
| Chiller delivery | 0d | 5d |
Earned value dashboards for a water transmission pipeline
A multi-table Power BI model connecting the schedule, the bill of quantities and site progress. DAX measures calculate budget at completion, earned value, actual cost, CPI, SPI and the estimate at completion.
- Separate views for the chief operating officer, project manager, construction manager and project controls manager
- BOQ items mapped to schedule activities
- Foreman and engineer performance and resource utilisation