Work that shows how we think

Selected dashboards, controls and tools built by the Ascendix team.

Power BI and project controls

Earned value dashboards for a water transmission pipeline

A multi-table Power BI model connecting the schedule, the bill of quantities and site progress. DAX measures calculate budget at completion, earned value, actual cost, CPI, SPI and the estimate at completion.

  • Separate views for the chief operating officer, project manager, construction manager and project controls manager
  • BOQ items mapped to schedule activities
  • Foreman and engineer performance and resource utilisation
Autodesk Construction Cloud

Cost and payment dashboards for a residential development

Power BI reporting on Autodesk Cost Management data, including a payment gate dashboard. Budget codes act as both zone and budget identifiers, and assets link to budgets through a budget code attribute.

  • Data model rebuilt around the budget code
  • DAX measures debugged and documented
  • Missing helper columns traced back to unpopulated source attributes
Aerial view of a large construction site
Progress reporting

Weekly progress dashboard for a master-planned development

A progress dashboard that turns site quantities into one weekly view for site and management teams, by zone and discipline.

  • Planned against actual progress by zone
  • One source for site and management reporting
  • Built for weekly refresh
BIM coordination reporting

Coordination dashboard for a multi-discipline building model

A weekly view of open clashes, issues and model health that turned coordination meetings from clash-by-clash reviews into decisions by zone and discipline.

  • Clash trend by week and discipline
  • Model health score from automated checks
  • Issues exported as BCF with owners and due dates
Ascendix tool, in development

Automation for Autodesk Cost Management

A Power Apps front end on Autodesk Construction Cloud cost data, connected through Autodesk Platform Services and reported in Power BI, to remove manual cost data entry.

  • Power Apps for structured cost entry
  • APS integration with ACC
  • Power BI reporting on the same data
Ascendix toolkit

Revit QA/QC before every issue

Checks that keep large models usable and 4D-ready: Activity ID parameters populated, worksets organised for fast opening, and schedules that take you straight to the element.

  • Activity ID checks for 4D links
  • Selective workset loading for large models
  • Batch extraction with pyRevit and APS
Ascendix standard

One code across schedule, cost and model

A structured coding format that ties every P6 activity, BOQ line and model element together, mapped to CSI MasterFormat and Uniclass, so dashboards reconcile by design.

  • Shared code across P6, BOQ, Revit and Power BI
  • MasterFormat and Uniclass mapping
  • Validation rules at data entry
MEP layer of the reference model
Ascendix reference model

A 12-storey model for 4D, clash and scan workflows

The interactive model on our home page: structure, facade and MEP with a tower crane and a 52-week sequence, used to demonstrate 4D, clash checking and point cloud workflows.

  • Three disciplines with layer control
  • 4D sequence across 52 weeks
  • Point cloud and clash views

Client names, project names and locations are withheld for confidentiality. Sample screens use illustrative data.

See new work as we publish it

We share methods, dashboards and lessons from current work on LinkedIn.

Follow Ascendix on LinkedIn

Want this on your project?

Tell us about the project and the decision you need to make. We will suggest the smallest piece of work that proves the value.